SCHEDULING

3D Models can be used to graphically represent any construction or operational Phase assigned to Equipments and Piping Lines.

The procedure is the following:

 

PHASES

Project Phases definition is done in the data base module with the option:

Sheduling Phases

For Equipments, the corresponding option is selected in the Equipment/Line menu. The following window opens, which allows to load Phases assigned to Equipments. In this example, two phases are defined, corresponding to 50% and 100% of the equipment construction.

Equipment Phases

The Scheduled Color is used to change to that color those equipments which on the analysis date have the corresponding phase completed, with regards the Scheduled Date. If there are more than one completed phases, the last one is considered.
The Delay Color is used to change to that color those equipments that have a phase with the analysis date falling between the Scheduled and Real dates, in case they have the Real date defined.
Equipments that have not any phase completed or delayed are set off.

 

EQUIPMENT DATES

Dates to Equipments phases are defined by the option:

Browse Equipment Schedule

that opens the following window, where Scheduled and Real dates for each equipment and phase can be loaded. The Real date is used only if delays have to be analyzed, otherwise is left blank:

Equipment Phases Dates

This table contains all Equipments inside all 3D models of the project and is automatically updated. It is also possible to load for each equipment its weight and painting area to automatically compute the Total weight an area by phase and date with the option:

Equipment Weight and Area by Phase and Date

that opens the following window:

Equipment Weight and Area by Phase and Date

A report to a text file will than be generated including only those equipments that, for the selected phase, have a date less or equal to the analysis date. The Total weight and area for those equipments are also computed.

 

LINE DATES

Dates assigned to each Line Phase are defined with the option:

Line Schedule

that opens the following window, where Scheduled and Real dates for each line and phase can be defined. The Real date is used only if delays have to be analyzed, otherwise is left blank. In this example, two phases are defined, corresponding to the completion of all line Spools and to the Whole line:

Line Phases Dates

This table contains all Lines defined inside all 3D models of the project and is automatically updated. The weight and painting area to each line is also automatically computed. With the following option the Total weight an Area by phase and date can be computed:

Line Weight and Area by Phase and Date

that opens the following window:

Line Weight and Area by Phase and Date

With the Accept button, a report to a text file will be generated including only those lines that, for the selected phase, have a date less or equal to the analysis date. The Total weight and area for those lines are also computed. Each phase is assigned to the whole line, so in this example, the line weight is always the weight of the whole line.

 

GRAPHIC ANALYSIS

Once equipment and line date scheduling are completed, from a 3D model opened with an EPLANT-Piping session (it can have other models attached as xref), the following command can be executed:

Date Schedule

that opens the following window:

Date Schedule

Selecting the Scheduled button, the command searches for each equipment and line if there is a phase with its Schedule date finished by the analysis date. For these Equipments and Lines it assigns the color corresponding to each phase. Those Equipments and Lines that have not any phase completed are set off.

Selecting the Delay button, the command does the same as the previous option, but controls also if there are equipments and lines with analysis dates falling between scheduled and real dates. In this case, the color for delays corresponding to each phase is used.

Selecting the Setup button, all equipment and line layers are reset on and changed to the project setup colors.

 

Last updated November 30th, 2020.